    Hello,

    I am currently working on in year 18/19 and forecasted data for 19/20.

    Our MIS system currently pulls the following as an example.

    Start Date: 13.03.2017
    End Date:13.09.2018
    Withdrawal Date: 13.06.2017

    The MIS system takes into account the end date and places that within 18/19 data, even though the learners withdrawal was effective in 17/18.

    Is this correct?

     
    #380893

    steveh
    Participant

    Hybrid End Year (which defines which year an aim falls into for QAR purposes) is the latest of Planned End, Actual End and reported year, so your MI System is working perfectly 😉

     